Court denies SK hynix, city bid to end lawsuits aimed at stopping $4B project in West Lafayette

Cases challenging 2025 rezoning decision may go to trial Dec. 1, a judge denies motion for summary judgment. Plus, more GOP names surface to replace Sen. Alting if he wins, then resigns in District 22

Dave Bangert's avatar
Dave Bangert
Oct 25, 2026
∙ Paid
  • Support for this edition some from Wintek Business Solutions. Weekend help for technical support is not something you’ll get from larger, non-local providers. But it’s just the way Wintek Business Solutions does things. No chatbots with canned responses. No dragging feet for onsite troubleshooting. Just an unrivaled commitment to local, 24/7 network support that defines Wintek’s public service heart to serve businesses and communities. Ready to gain the advantage of local support? Call 765-742-8428 or visit wintekbusiness.com.


COURT DENIES SK HYNIX, CITY BID TO END LAWSUITS AIMED AT STOPPING $4B PROJECT IN WEST LAFAYETTE

An attempt by SK hynix and the city of West Lafayette to call “game over” before a trial started for a pair of lawsuits from West Lafayette residents fighting the placement of the South Korean company’s $4 billion semiconductor facility was rejected last week.

In an Oct. 22 ruling, Tippecanoe Circuit Judge Sean Persin denied a motion for summary judgment filed in late 2025 by attorneys for SK hynix, the city and Purdue Research Foundation, confirming a trial date.

Persin did not go into detail in last week’s order about the factors for his decision.

But in court filings and during a three-hour hearing Sept. 29, attorneys for the company and the city had argued that the West Lafayette City Council got it right when it voted 6-3 in May 2025 to rezone 121 acres north of Kalberer Road from single-family residential to heavy industrial uses.

Work continues on SK hynix’s $4 billion project in West Lafayette. (Photo: Dave Bangert)

The city council’s actions, they’d argued, met a rational basis test needed to justify the vote on a rezoning that cleared the way for SK hynix to build a facility expected to assemble semiconductor chips into high-bandwidth memory for the artificial intelligence market.

They’d argued that the court didn’t need to step into what amounted to a legislative decision, other than to grant summary judgment against the effort to stop construction and return the property to R1/single family zoning, just because the plaintiffs didn’t like the outcome.

Now, both sides are due in court Monday afternoon for a final pretrial hearing ahead of a bench trial starting Dec. 1. The trial is scheduled to go three days.

User's avatar

Continue reading this post for free, courtesy of Dave Bangert.